NFR - Network Facility Requirement

Indicates that the customer’s desired due date cannot be met because additional provider facilities are required to fulfill the request.

NOTE 1: Examples of provider facilities may include fiber builds, card installation, etc.

VALID ENTRIES:

Y = Required

USAGE: This field is conditional.

NOTE 1: Required on the initial confirmation notice when a need for additional facilities is identified and will cause the DD to be greater than the DDD field on the ASR Form, otherwise prohibited.

DATA CHARACTERISTICS: 1 alpha character

EXAMPLE: Y