AENG - Additional Engineering

Indicates that if additional engineering is required, an estimate of the charges is to be forwarded to the initiator of the request.

NOTE 1: This engineering activity is ordered from applicable state tariffs, not from Inter-state Access Tariffs.

NOTE 2: Additional technical information after the provider has provided the Design Layout Report (DLR ), may be billable as additional engineering.

VALID ENTRIES:

1 = overtime engineering

2 = engineering connections when more than one provider is providing the access service

3 = overtime engineering and engineering with other providers

4 = other engineering

USAGE: This field is conditional.

NOTE 1: Optional when the ACT field is “N”, “C”, ”M” or “T”, otherwise prohibited.

DATA CHARACTERISTICS: 1 numeric character

EXAMPLE: 3